Regional electricity company-
Driving operational
performance improvement
Download
case study>
File size 81k
The challenge
The network maintenance division of this
regional electricity company was losing money and failing to deliver profit
improvements promised to shareholders. Forecast losses of up to £40
million for 2002, an increasing number of customer complaints and the threat of
penalties by the regulator meant rapid corrective action was needed.
Poor management of the 2200 field staff meant over 40% of work was carried out
at premium overtime rates. A belief existed amongst project engineers that the
field staff were shirking, starting late, leaving early and deliberately
running into overtime. Theft of equipment from stores was also on the
increase.
Approach
Led by three Corven
interim managers, the turnaround of business performance was structured into
three phases.
Phase One
The first six weeks
focused on identifying the root causes of poor performance, setting the
strategy for the following year and on quantifying, prioritising and launching
quick wins. The initial challenge was to gain dependable management
information (since current data was unreliable due to problems with a new SAP
system), by developing a new cost model for the key business areas. This
analysis demonstrated that low field staff utilisation was caused more by poor
workflow management by project engineers at head quarters than by lazy field
staff.
At the same time, Corven worked with the Managing Director to
develop the strategy and key business objectives for the following year. With
the vision of the business clear, a review of all ongoing internal projects led
to 28 non-value adding initiatives being stopped and resources reallocated to
quick win activities focused on improving the organisations top five
performance measures.
Phase Two
Over
the following eight weeks, Corven worked with a Change Team to improve field
staff utilisation, to renegotiate civil contractor agreements, and to
communicate the strategy to the organisation.
The initial focus was
to deliver a new resource allocation tool that improved the flow of work from
project engineers at head quarters to the field staff. Thirty Foremen were
recruited from outside the utility sector, put through an intensive two-week
training programme, and rolled out across the network, area by area. Their job
was to monitor performance and to increase utilisation of staff by pulling work
from head quarters.
During the same period, the Corven team ran a
number of workshops to scope out the requirements for new civil contractor
agreements. Corven facilitated a number of events to gain alignment with the
Board on the strategy. A communications plan was launched and posters, leaflets
and informal breakfast meetings between directors and field staff were
introduced. By the end of the eight weeks a series of roadshows were launched
to communicate the new strategy and business objectives to the whole
organisation.
Phase Three
With the
utilisation of field staff dramatically improved, the focus now moved to
driving productivity and skills transfer. After building an improved working
relationship with the unions, field staff were encouraged to develop a broader
range of skills and agreed to be transferred to different locations to get a
better skill balance across the network. Overtime was stopped except for
emergencies and the use of contractors was eliminated for several classes of
work. New standard hours for jobs were introduced and monitored by Foremen for
all activities.
Results
From a loss of
£33 million in 2001, the business created a profit of £10.8 million
the following year. Utilisation of staff across the network increased to almost
100%, with productivity doubling to 61% and overtime spend dropping by 85%.
Overall spend on civil contractors fell by 27%.
Improvements in
morale across the workforce were measured in the Employee Opinion Survey and
the entire change programme gained increased credibility from blue-collar
workers to shareholders.



